The vessel is in position in the dock, the water is being pumped out and she’ll shortly be high and dry on the blocks for final inspections, cleaning and painting.
Work continues on board at a rapid pace and she’ll remain in drydock until mid-September following which she’ll be towed out to the anchorage and her removable thrusters will be installed by divers using the cranes on board. Guinevere will then undergo her FMEA, DP trials and sea trials for final class approval with DNV and then hopefully around end October / early November she’ll be ready to depart for her first project.